Nek Ha · Work in progress — June 2024

The south wall is finished, the perimeter columns are poured, and the first foundation slabs go down on villas 1, 4 and 5.

Nek Ha · Work in progress — June 2024

Exterior infrastructure. Construction of the south wall was completed, and the concrete columns of the perimeter wall were poured.

Work on villas. Excavation of villa 6 was carried out. The foundation slabs for villas 4 and 5 were prepared, and the foundation slab for villa 1 was poured.

Gallery

Nek Ha · Work in progress — June 2024 — 1
Nek Ha · Work in progress — June 2024 — 2
Nek Ha · Work in progress — June 2024 — 3
Nek Ha · Work in progress — June 2024 — 4
Nek Ha · Work in progress — June 2024 — 5
Nek Ha · Work in progress — June 2024 — 6
Nek Ha · Work in progress — June 2024 — 7
Nek Ha · Work in progress — June 2024 — 8
Nek Ha · Work in progress — June 2024 — 9
Nek Ha · Work in progress — June 2024 — 10
Nek Ha · Work in progress — June 2024 — 11
Nek Ha · Work in progress — June 2024 — 12
Nek Ha · Work in progress — June 2024 — 13
Nek Ha · Work in progress — June 2024 — 14
Nek Ha · Work in progress — June 2024 — 15
Nek Ha · Work in progress — June 2024 — 16
Nek Ha · Work in progress — June 2024 — 17
Nek Ha · Work in progress — June 2024 — 18
Nek Ha · Work in progress — June 2024 — 19
Nek Ha · Work in progress — June 2024 — 20
Nek Ha · Work in progress — June 2024 — 21

What's new at Mycelium

Investor enquiry

Tell us what you are looking for

The more context you give us, the more useful our first conversation will be. We answer every enquiry personally.

WhatsApp