Nek Ha · Work in progress — June 2024
The south wall is finished, the perimeter columns are poured, and the first foundation slabs go down on villas 1, 4 and 5.
Exterior infrastructure. Construction of the south wall was completed, and the concrete columns of the perimeter wall were poured.
Work on villas. Excavation of villa 6 was carried out. The foundation slabs for villas 4 and 5 were prepared, and the foundation slab for villa 1 was poured.