Nek Ha · Work in progress — November 2024

The biodome begins: the steel reinforcement layer goes in, preparing the ground for the bamboo structure above it.

Nek Ha · Work in progress — November 2024

House 1. Plastering of the walls and the ground floor slab was completed.

Construction of the biodome began with the placement of the steel reinforcement layer, preparing the ground for the bamboo.

Additionally, wiring, conduit installation, drywall details and exterior plastering were completed, and the Maya stone finishes began.

Gallery

Nek Ha · Work in progress — November 2024 — 1
Nek Ha · Work in progress — November 2024 — 2
Nek Ha · Work in progress — November 2024 — 3
Nek Ha · Work in progress — November 2024 — 4
Nek Ha · Work in progress — November 2024 — 5
Nek Ha · Work in progress — November 2024 — 6
Nek Ha · Work in progress — November 2024 — 7
Nek Ha · Work in progress — November 2024 — 8
Nek Ha · Work in progress — November 2024 — 9
Nek Ha · Work in progress — November 2024 — 10
Nek Ha · Work in progress — November 2024 — 11
Nek Ha · Work in progress — November 2024 — 12
Nek Ha · Work in progress — November 2024 — 13
Nek Ha · Work in progress — November 2024 — 14
Nek Ha · Work in progress — November 2024 — 15
Nek Ha · Work in progress — November 2024 — 16
Nek Ha · Work in progress — November 2024 — 17
Nek Ha · Work in progress — November 2024 — 18
Nek Ha · Work in progress — November 2024 — 19
Nek Ha · Work in progress — November 2024 — 20
Nek Ha · Work in progress — November 2024 — 21

What's new at Mycelium

Investor enquiry

Tell us what you are looking for

The more context you give us, the more useful our first conversation will be. We answer every enquiry personally.

WhatsApp