House 1: Plastering of walls and ground floor slab was completed

Construction of the biodome began with the placement of the steel reinforcement layer, preparing the ground for the bamboo.

Additionally, wiring, conduit installation, drywall details, and exterior plastering were completed, and the Mayan stone finishes began.

House 3: Block erection and column assembly were completed, and the concrete pouring process began.

House 6: The foundation slab was poured, waterproofing was applied, and block erection began.
Amenities: Trees were transplanted within the designated construction area.