Houses 7 to 12: Excavation was completed and the formwork was poured in units 7, 8, 9, and 10.
House 6: Backfilling for the floor pour is progressing, and work is underway on the layout and formwork for the staircase.
House 3: Backfilling for the floor pour is complete.
Pond area: Cleaning is being carried out in preparation for pouring the concrete slab with reinforcing mesh and plastering the walls.
House 1: The exterior finish in Maya stone was completed, and formwork for the kitchen, bar, and bathrooms began Plastering continues on the upper floor
Bio-domo: The first layers of the dome were completed using steel, bamboo, and henequén.